It’s been a few weeks since I updated and it was, frankly, because work was happening at a snail’s pace and it was super frustrating to stare at the same house with the same progress day after day.

There seemed to be some confusion or communication issues that resulted in the concrete cutter being delayed which basically kept everything else from progressing. The concrete cutter was needed to remove the existing foundation walls. Fortunately, when it finally happened my in-laws were at the house checking in on things and caught a video of the last wall coming out. The 2x6s that you see are a temporary wall that is literally holding up the house since they cut out the foundation wall. There is also a closet wall that they left in place for now to bear some of the load. I am now afraid to walk into the house for fear the entire thing will come down. It’s a little freaky to look at the house in this condition.

Once the walls were out, they worked on getting the footings in place and the city came out to do an inspection yesterday. Mike got a call from the contractor asking if we were ever in contact with the engineer or if the engineer worked with the architect. After answering some of the questions Mike asked why they needed to know and it turns out we failed inspection because of the size of rebar used.

If this had happened a few weeks ago, I would have been on the phone tracking everything and everyone down, but I’ve almost become desensitized to “today’s issue” already and finally last night just asked Mike to text the contractor to see if he got it resolved or not. He said they did, but we didn’t even ask what the resolution was exactly. I’ve also started to become desensitized to seeing things I didn’t expect to get ruined to be ruined. There are parts of the fence I didn’t expect to see ripped out and also fence posts the crews have backed into that would have been upsetting at first, but now it’s just adding to the list of things that we’ll just figure out as we go.

We had another inspection scheduled for today at 12:30 and we must have passed because when I got home today we had footings in place.

When I got home there was also an inspector at the from the construction loan company. The way our construction loan works is that there are several loan draws and the inspector comes out at each draw to make sure the work that the contractor says has been done is actually done and acceptable. He seemed very nice and asked me some questions about the temporary power and work being done. I’m anxious to see the details of the first draw because it will be the first time I start seeing how the bid compares to actual amounts spent.

We also started having some power issues this week on the trailer. We noticed that our phones were suddenly losing power when charging at night, like the power is almost cycling high and low. It was noticeable because my phone vibrates each time it gets plugged in and it was vibrating every few seconds. We also noticed that the fans run at high speed then for a second seem to run at a lower speed before picking back up. This has happened a few times that we’ve noticed and then last night the power went completely out for a few seconds. I remember Mike getting up and walking around, but I was so exhausted I remember nothing other than that. It came back on and seemed fine for the rest of the night.

A coworker of mine recommended a mobile RV repair guy when he found out we were embarking on this journey and I called him this morning. The soonest he can come out is next week. I had no idea there were mobile RV repair men until just a few months ago, but I’m thankful for them right now because the thought of having to take the trailer to the “shop” for a few days is daunting. I would have to pack it up so that stuff wasn’t flying everywhere when we moved it and then also get us moved out for a few days- instead, he’ll come to us!

In the middle of all of this, the baby turned 1 yesterday! I am not sure how it’s been a year. She is teething like crazy and super grouchy at night when she is sleeping. As a result, so she often ends up in our little trailer queen size bed with us. I don’t mind the extra snuggles during this period of total chaos. Except when she open hand slaps me in the face to see if I am awake.

Can’t you live in the house during the renovation?

Lots of people have asked me this question and I think this video pretty well sums up why that isn’t possible.

The house, for the most part, is being completely demolished other than one room upstair and downstairs and the garage. This, combined with the fact that our Construction Loan doesn’t allow for it are the main reasons we couldn’t stay in the house and also had to move out all of our stuff. We can’t move back in until the city issues us a certificate of occupancy.

When Inside Becomes Outside

I know you are all losing sleep over this like I am, so here are your updates!

First, the insurance saga continues. I think we are close to figuring out a solution, but it’s a few more hundred dollars out of pocket to make sure we have the appropriate insurance to protect the entire property and our belongings. The long and short of it is that there never should have been a change requested to our policy, but since there was the insurance company rejected the new coverage which resulted in the cancellation of our homeowners insurance.  It’s extra complicated by the fact that we have out buildings (barn and detached garage), not just the property under construction. Lesson for those at home that ever take on a project like this is that you should talk to your insurance provider, figure our if it makes the most sense for you to carry the policy or your contractor, have them document everything, and never close on a loan when your insurance guy is on vacation.

Also, the labeling didn’t really work on everything in the house, I almost cried when I discovered this cabinet had been junked. Not because I was sad about the cabinet, but mainly because Mike was right when he told me the week before that we should just take the time to remove it so nothing happened to it. I kid. We saved all the upstairs cabinets to potentially be reused downstairs if we put in a mother-in-law apartment and this was the last one to the set. Heartbreaking.

Last week they got the east foundation dug out. See the house plans here if you aren’t familiar. It’s a crazy big hole even though the house is only coming out about 5 feet on that side.  The gas company hadn’t come out to move the gas yet, so they couldn’t finish that side out completely.

A few more photos from that stage that I never got around to posting last week are below.

Darwin took one look at the hole and wagged his finger at the excavator and said, “No, no, no.” He told me that the tractor made a huge mess and it was in trouble. He still tells me that the tractors stole the house, but they are going to put a new one in the hole so it’s okay. Poor little guy, it’s a lot to take in!

We have to pay to have all this dirt trucked out of here, so I am working on finding people on Facebook that want it all. Who knew that dirt brokering was such a lucrative business? Tomorrow we hopefully have a couple coming to get it all for their back yard and that will save us some money.

Fast forward to today and now all the sudden inside is outside and outside is inside because windows and walls are coming out!

A lot of demo has been done, but there is still a lot to do. Both the bathrooms still need to come out, the exterior of the entire house is coming off, and there are exterior walls that need to be removed, including large sections of the existing foundation. We are on our second dumpster already and there is so much more that needs to go.

We don’t have internet again. When they took the utility panel off the back of the house, the cable apparently ran through it. Darwin is devastated that Netflix is not working. We do have a port-a-potty though, so that’s a pretty good trade-off, right? I am hoping Darwin never discovers what it actually is or I will be taking 11pm trips to the port-a-potty, I guarantee it!

We met with the contractors and are finishing up most of the color selections and finishes. We have all the flooring, all the tile, the exterior finishes, and the cabinets picked. We just need to finish up by selecting countertops, backsplash tile, and a paint color. It’s a lot of work and it’s hard to visualize it all coming together so it will be exciting when it does. I feel like every time we meet we think of something that we didn’t specifically include in the bid like window well covers, an outside railing around the new basement stairs, egress ladders, etc. I really like our contractors though. They are very on top of things and pretty calm and collected which makes me feel better.

Trailer living is trailer living. I think the only part I really hate is dishes. Our sink is so small and the kitchen really has no space to dry everything. I need bottles for Trixie so it’s a bit of a never-ending process. Showers are similar, the shower has hot water and works just fine, but it’s just so small and I love a good bath so it’s hard to get used to really fast and cramped showers. Laundry is sometimes a problem, but not too bad. Mike had to run to his parents and do an emergency load of kid bedding on Monday for the first time, but at least we have options. We accidentally unplugged the trailer this weekend when we went to the lake house and lost all the food in the trailer fridge- we just weren’t thinking about it and were so used to closing everything up like we did before when we were hooked up to a converter. It’s been hot in Utah this week, a few days in the triple digits, but we’re decently comfortable all things considered. It just takes a while to cool the trailer off when we get home at night. It has pretty good storage everywhere except the kitchen and in our room, but having so much space in the garage and that being so close means thats not too big of an issue.

I’ll try to update again this weekend as I suspect there will be lots of big noticeable changes around here the rest of the week!

 

Grab Another (Cold) Beer

I meant to post this days ago, but it seems like the days are getting away from me. This process has been really involved every emotion you can think of and unfortunately this week there was a lot of sadness, angst, stress and anger.

I won’t go into all the details, but we decided to put one of our feral cats down after he started becoming increasingly aggressive. It’s something that has been a problem for a while now and all the activity and strangers in and out of our house were causing a real problem for him. It was a very hard decision because he was a good cat when no one else was around and it makes me feel guilty and selfish that our decision to do this project contributed to his behavior.

Mike buried him near the barn and I had a little talk with him that night when I got home from work (Read: I bawled my eyes out while no one else was there to watch). I then spent the rest of my night burning off my sadness and anxious energy by hauling boxes into the garage. I went to get myself a beer and the fridge as a reward, but it wasn’t cold. The fridge was busted. At 10pm I was off to the Maverick to buy ice so we can save our food. Fortunately, it was pretty slimmed down because we are expecting to be without power for a (hopefully short) period of time next week between when they turn off utilities to dig and when they get temporary utilities in place. We replaced the motherboard in the fridge about a year ago– lesson here is that I am never buying LG appliances again. A dryer, fridge and crappy dishwasher later.

We were hoping to have this fridge in the garage so we weren’t stuck with a tiny trailer fridge the whole time, but we’ll have to figure out something else. I literally cannot spend brain energy on this right now if I am going to keep functioning and get us moved out of the house on time.

This all happened on Wednesday. I had no idea that Thursday would get worse. We were back and forth with the loan company about the construction loan and the insurance that was needed and who talked to who and blah blah blah. We NEED to close by the end of the week because heavy machinery will be at my house Monday at 8am to dig a giant hole. If we don’t close and they dig, we’re spending money that we don’t actually have. That’s a problem! No one was actually willing to commit that we would close Friday so that was pretty stressful.

Then, I got a call about 3pm Thursday that they miscalculated the loan amount. They forgot to adjust the payoff amount on our HELOC to the correct number from our last meeting. We had to choose whether or not to fix it and delay closing or bring $4,500 to closing. We decided to find the money (I just added a money tree to the plans!) and continue with the closing Friday since the ramifications could be even more costly if we don’t close.

Early on in this process I was reading some posts on reddit that talked about keeping as much of your cash liquid as possible going into a home renovation and I’m really thankful for that right now. I changed the way I managed our money in the last 6 months knowing that this project was coming and it really saved me this week, even if it doesn’t make it sting any less.

I watch all those shows on HGTV and think that home renovations seem really stressful and they must just be editing it for added drama. Nope, it’s really just that stressful and the project hasn’t actually started.